HST Rebate Active — Save up to $130,000

Quick Answer

A modular home in Ontario takes 4–7 months from contract to occupancy: permit approval (4–8 weeks), factory build (12–16 weeks, runs concurrently with site prep), delivery and crane-set (1–3 days), finishing and inspections (4–6 weeks).

The Complete Timeline

What makes modular faster than site-built is the parallel process — your home is being built in the factory while your site is being prepared simultaneously.

Phase 1: Contract and Design (Weeks 1–4)

Sign purchase agreement, select floor plan and finishes. Manufacturer confirms order.

Phase 2: Permits (Weeks 2–10, parallel)

Dealer submits permit application to your municipality. Municipal review: 4–8 weeks. Permit issued — foundation contractor engaged.

Phase 3: Factory Build (Weeks 4–20, parallel)

General Coach begins construction while permits process. Typical factory build time: 12–16 weeks. Third-party CSA A277 inspector present throughout.

Phase 4: Site Preparation (Weeks 8–16, parallel)

Site clearing, foundation construction (3–5 weeks), utility rough-ins. Running concurrently with factory build.

Phase 5: Delivery and Crane-Set (1–3 Days)

Modules transported and lifted onto foundation by crane. Typically 2–4 loads per home. Modules bolted together and sealed.

Phase 6: Finishing (Weeks 4–6)

Mechanical, electrical, plumbing connections. Interior finishing, exterior work, deck and steps.

Phase 7: Occupancy Permit

Final inspection, occupancy permit issued, keys handed over. Total: typically 20–28 weeks (5–7 months) from contract.

What Causes Delays

Delay SourceTypical Impact
Permit processing2–8 weeks added
Change orders1–4 weeks added
Foundation issues (soil)1–3 weeks added
Utility installation2–6 weeks added
Winter weather (site work)1–4 weeks added

vs. Site-Built

Build TypeTypical Timeline
Modular (Ontario)5–7 months
Site-built (GTA)12–24 months
Site-built (rural Ontario)10–18 months

Frequently Asked Questions

Can I move into a modular home in winter in Ontario?

Yes — the home is factory-built in a climate-controlled environment so winter weather does not affect the home build. Site work is slower in winter. Plan for a spring or summer move-in if possible.

What is the fastest a modular home can be completed in Ontario?

Under ideal conditions — pre-approved lots with existing services — a modular home can be completed in as little as 16–18 weeks from contract. 20–28 weeks is more typical.

Does the timeline change for a 55+ community?

In Fountainhead Villages communities, infrastructure is already in place — roads, utilities, foundation pads. This compresses the timeline to primarily the factory build period plus finishing.